"Even these recommendations say we have 10 years, that's a decade, that's a long time." Charlotte County Commission Chairman Joe Tiseo said that at the May 12 commission meeting, according to the Boca Beacon. He was arguing for the quick fix: patch the old railroad trestle at the end of Pier Road, let people fish from it again, and plan a new pier later. He lost the vote 3-2.
That vote is why the Placida Fishing Pier stays closed this fall, and why the county's own schedule runs to 2030. The county had a faster way to reopen it. Commissioners passed on it because a repair would have meant paying for the same pier twice.
Ten years was the number that decided it
Charlotte County hired Coastal Engineering Consultants, known as CEC, to design and permit the rebuild at 13120 Pier Road. CEC's first job was to sketch alternatives that would hold up better in storms, meet ADA rules and line up with FEMA guidance. The county's May 12 presentation laid out three choices for the pier deck itself.
| Pier option | What it involves | Estimated cost | Tradeoff |
|---|---|---|---|
| Option 1: repair | Rebuild the displaced base section, drop the twisted 30-foot end, fix decking and rails, add ADA improvements | $240,000 | Fastest permitting and fastest reopening; same storm resilience as before |
| Option 2: timber replacement | New 9-foot by 660-foot timber pier on the existing alignment, over the existing jacketed piles | $2.7 million | Much better storm resilience; prolonged state and federal permitting |
| Option 3: hybrid replacement | New pier on steel pipe piles with concrete caps and synthetic decking | $6.26 million | Highest cost and longest timeline |
CEC recommended the repair. It listed the lowest cost, permits that were easier to get, less creosote-soaked timber going to the landfill, and keeping a historic structure. It also said the repair "can restore public access fastest."
County staff recommended the $2.7 million timber pier. Their written reason was one line: the current structure "only has a life expectancy of 10 years before full replacement is needed." A $240,000 repair would have bought roughly a decade, and then the county would face the full replacement anyway at whatever it costs then.
Commissioner Bill Truex framed it the same way at the meeting. "The longer we wait the more expensive it's going to be and if we do it twice, it's going to be even more exponentially expensive," he said, as reported by the Boca Beacon. Commissioners Ken Doherty and Stephen R. Deutsch sided with staff. They acknowledged it would take longer, especially with federal agencies involved. Tiseo and Commissioner Chris Constance voted no. Constance had floated a quick fix now with a replacement planned for later.
The slow part is the path out to the pier
CEC split the project into three pieces: the causeway path that leads out over the water, the backwall at the base of the pier, and the pier itself.
The backwall had one design. A precast concrete seawall moves 12 feet waterward to mean high water, with two 20-foot return walls and the asphalt path carried through to the pier. Because all of it sits above mean high water, it only needs an exemption check from the Florida Department of Environmental Protection (DEP), with no federal sign-off. The Beacon put its cost at $259,000.
The causeway is another matter. Restoring it to its pre-storm shape was the cheapest option at $592,000, and it could be permitted without federal approval because the footprint would not change. Both CEC and staff recommended Option 3 instead, at $844,000. It hardens the causeway, widens the crown to push breaking waves away from the walking path, and adds terraced shelves planted with red mangroves on the seaward side. That fill extends past mean high water into sawfish habitat. The county presentation says work there needs federal permitting and consultation that could take "well over a year."
Added up, causeway, backwall and timber pier come to about $3.8 million by the Beacon's count. The county's project page shows a total budget of $3,480,000, funded through FEMA Public Assistance. County Community Services Director Tommy Scott told commissioners that every option followed FEMA rules and would be eligible for reimbursement, the Boca Beacon reported.
What the October plans show on paper
The project moved on Tuesday, October 6. That day DEP published the plans CEC had submitted for the rebuild, as the Boca Beacon reported the next day.
The filed drawings follow the plan commissioners chose. The existing creosote timber piles, already wrapped in concrete jackets, stay in the water so the creosote isn't released. The staff plan also called for keeping the old piles for their habitat value. On land, the plans show an 8-foot-wide asphalt path on stabilized subgrade, new mangrove plantings, and some of the existing riprap reused.
Keeping those piles ties the new pier to the oldest thing out there. The county's presentation describes the structure as a railroad trestle built in the early 1900s to ship phosphate. After the rail line was vacated in the early 1980s, the north trestle became the fishing pier.
The pier's timeline, from rails to the county's 2030 estimate
- 1905 to 1913. The Boca Grande Historical Society timeline dates the start of railroad construction to 1905, the Boca Grande to Arcadia line to 1907, and the end of all track construction to 1913.
- Early 1980s. The rail line is vacated and the north trestle becomes a fishing pier.
- 2024. The pier is badly damaged in the 2024 hurricanes and closes. The county's project page lists Ian and Milton as the storm events for the pier work.
- May 12, 2026. Commissioners vote 3-2 for the timber pier and the mangrove causeway.
- October 6, 2026. DEP publishes CEC's submitted plans.
- September 9, 2030. The estimated completion date on the county's project page, where the pier work is still listed under "Design and permitting."
The county says pier reconstruction everywhere must go through engineering, permitting, environmental review and contractor selection before construction can start. It also says permitting through agencies such as the U.S. Army Corps of Engineers can take 12 to 24 months. A July 21 county column, "County making progress on damaged fishing piers," says the new Placida pier will be rebuilt at a higher elevation. It is in design and permitting and goes out to bid for construction once that work is done.
Where a line can go in the meantime
The Boca Grande Fishing Pier at 5810 Gasparilla Road in Placida is also closed. It lost parts of its parking area, its natural canoe and kayak launch, its walkway and its bulkhead to hurricanes. Its county project page lists the work as design and permitting, with a $978,600 FEMA Public Assistance budget and an estimated completion of October 1, 2028. Ian, Idalia and Milton are the listed storms. That project is further along than Placida's. According to the county's July 21 column, the U.S. Army Corps of Engineers approved its permit on June 30, 2026, and the work will go out to bid with a contract coming to the board at a future meeting.
Charlotte County's facilities status page lists seven fishing piers closed for restoration. Besides Placida and Boca Grande, they are Anger, Bayshore West, Bayshore East, El Jobean and Port Charlotte Beach. Two county piers are open as of the county's current listing. One is Centennial Fishing Pier, which the county column places at 14021 Gasparilla Road in Placida. The other is Chadwick Park Fishing Pier at 1857 Gulf Boulevard in Englewood.
Next on the calendar is federal review of the causeway work in sawfish habitat. Commissioners voted in May knowing that review would take time, and that the repaired trestle would have needed replacing within about ten years.
The Moore Team keeps up with county projects like the trestle pier because they shape daily life on our stretch of coast. If you'd like to talk about the Placida waterfront, the harbor side of the island, or how projects like this rebuild figure into a property decision, Jeff Moore would be glad to sit down with you. Book a Private Consultation.